Inverter and cable settings
How many strings feed one inverter or string monitoring box, whether cables are routed and measured, and what a manufacturer inverter file changes.
This group sets how the plant's DC output is collected and converted, how much of it one piece of collection equipment takes, and whether the application routes and measures the cables between the tables and the control rooms. Its title and its fields follow the electrical mode you chose at launch, because the two topologies collect the strings in different places. See Choosing a design mode for the choice itself.
One definition governs everything on this page. A string is one row of modules within an MMS-Table (MMS — module mounting structure). A fixed-tilt table configured with two rows therefore carries two strings; a half table carries half the strings of a full one. Everything you set here is counted in strings, so the table configuration and this group are two ends of the same decision — see Table configuration.
The group in each mode
| Electrical mode | Group title | Where the strings are collected |
|---|---|---|
| String Inverter | String Inverter | String inverters distributed across the plant, each converting DC to AC where it stands and sending AC onward |
| Central Inverter | SMB – String Monitoring Box | String monitoring boxes distributed across the plant, each collecting strings and passing DC onward |
In Central Inverter mode the string monitoring box — SMB — is the collection point. It does no conversion: it gathers the strings assigned to it and sends their combined DC output on to a central inverter, which sits inside an ICR (inverter control room) rather than out in the field. The field equipment and the conversion equipment are separate objects in that mode, and the group gives you a field for each.
- What it shows
- The whole group in String Inverter mode at its defaults, with the cable option unticked and no inverter file loaded.
- How to get there
- Choose a String Inverter mode at startup. Nothing changed from defaults.
Two fields and a file row: how many strings one inverter may take, whether cables are calculated, and which inverter file the AC side is sized from.
Maximum strings per inverter
The first field caps how many strings one collection point is allowed to take. The application clusters the placed tables and puts down as many inverters or monitoring boxes as the cap requires, so a lower number means more equipment, each covering a smaller group of tables.
| Field | Default | Range | What it does |
|---|---|---|---|
| Max strings per inverter | 20 | 1–500 | The largest number of string cables one string inverter accepts |
Set this from the inverter or monitoring box you intend to buy, counted the way the application counts: one string per row of modules in a table. The number of modules in that row does not enter into it — a row is a string whether it holds few modules or many. What the row holds decides the string's voltage and current, which is a separate question, settled by automatic string sizing.
The DC capacity that ends up attached to each unit is reported in the summary
table, as Inv kWp in String Inverter mode and SMB kWp in Central Inverter
mode, alongside the count itself. See
Summary table columns.
Maximum SMBs per central inverter
Central Inverter mode only.
| Field | Default | Range | What it does |
|---|---|---|---|
| Max SMB per Central Inverter | 10 | 1–200 | The largest number of string monitoring boxes whose DC trunks land on one central inverter |
This field and the one above it multiply out to the capacity of a central inverter:
Central inverter capacity = SMB capacity × Max SMB per Central Inverter
So the two fields are the whole DC-side sizing chain in this mode. The strings
per SMB fix what one monitoring box collects; the SMBs per central inverter fix
how many of those collections one machine converts. Change either and the
central inverter count changes with it, reported as C.Inv and CInv kWp in
the summary.
One ICR building houses up to four central inverters. The control rooms themselves are sized and placed from the ICR Block capacity in the site parameters, not from this group — see Control rooms.
Calculate Cables for PV Power Plant
Off by default. With it off, the layout is generated, the equipment is placed and counted, and no cable is routed. With it on, the application traces every run and reports its length.
What gets traced depends on the mode, because the conversion happens in a different place:
| Run | From | To | Counted |
|---|---|---|---|
| String cable (DC) | Each table | Its string inverter | ×2 — once for the positive conductor and once for the negative |
| AC cable | Each string inverter | The nearest ICR | ×1 — a single three-phase run |
The inverter converts in the field, so the run into the control room is AC.
Lengths appear in the summary as StrDC(m) and AC-ICR(m).
Medium-voltage runs from the control rooms onward are a separate matter, routed in both modes. Conductor lengths and trench lengths are reported separately, because several cables share one trench. See Cable routing.
The notice that appears when you tick it
Ticking the box raises a notice before anything is enabled: cable calculation can take a long time on large or complex layouts, and the recommendation is to generate the layout first without it, review what you get, and enable it for the final run. The buttons are Enable Now and Not Now (Recommended) — and the recommended one, which does not enable cable calculation, is the default.
- What it shows
- The notice with its full text and both buttons, so the recommended choice is visible.
- How to get there
- Tick the cable calculation option. The notice appears immediately.
Take the recommendation on a plant you have not laid out before. Cable routing is the slow step on a large plant, and it is the step whose result you are least likely to keep: change the table configuration, the perimeter road, the ICR block or the strings per inverter, and every run is traced again from scratch.
Why it is slow is worth knowing, because it tells you when it will not be. The AC runs are traced as horizontal and vertical segments only — no diagonals — and every candidate path is checked against the usable area before it is accepted, so a run may cross the perimeter road band but never leaves the plant fence. The work therefore grows with the number of tables and with how broken up the usable area is: a rectangular site with a clean fence routes far more cheaply than the same area cut by canals, water bodies and steep ground. On very large plants the application falls back to a fast geometric estimate of cable length so that generation stays quick.
What you still get with cables off
- The inverter and monitoring box counts are computed anyway. So are their capacities, the central inverter count, and everything downstream that depends on them — the AC capacity, the DC/AC ratio, the single-line diagram and the bill of materials.
- The cable columns of the summary show a dash. A
—inStrDC(m),AC-ICR(m),DC-CInv(m),MV(m)or any trench column means the value was not computed, not that it is zero. - The DC, AC and MV cable view switches have nothing to draw, and the cable layers are left out of the CAD export.
Everything else about the design is final. Only the cable numbers are missing, and one more run with the box ticked fills them in.
Loading a manufacturer inverter file
The group carries a row for a PVsyst inverter file — the .OND file the
manufacturer publishes for the machine you intend to buy. Click Load .OND
and pick the file.
- What it shows
- The inverter file row after a file has been loaded, showing the make and model, with the View button now enabled.
- How to get there
- Click Load .OND and pick an inverter file.
The file settles the AC side of the design:
- The maximum AC output drives the plant AC capacity. The application takes
the file's maximum AC output as the rating of one machine and reports the
plant's AC capacity from it —
AC(MWac)andInvCap(MW)in the summary. - The DC/AC ratio follows. With a DC capacity from the placed modules and an
AC capacity from the file, the ratio is reported as
DC/AC. It is the number a reviewer looks at first, and without an inverter file there is nothing to divide by. - When the file declares no maximum output, the nominal power is used instead. Some files carry only a nominal rating; the design still sizes, from that figure.
Viewing what was read
View opens the file read-only, laid out the way PVsyst presents it, so you can confirm the machine before designing around it. The tabs are Main parameters, Efficiency curve, Additional parameters, Output parameters, Sizes and Technology and Commercial data.
- What it shows
- The viewer on its first tab with the whole tab strip visible.
- How to get there
- Load an inverter file, then click View next to it.
The Efficiency curve tab draws efficiency against load from the points in the file. Read it against the inverter loading your DC/AC ratio implies: a plant run at a high ratio spends most of its hours in the upper part of that curve, and the conversion loss you enter in the yield calculation should agree with what the curve shows there. That loss is a separate input — see Loss assumptions.
- What it shows
- The efficiency curve tab with the curve drawn and axes readable.
- How to get there
- In the inverter file viewer, open the efficiency curve tab.
The file is also what makes automatic string sizing possible
The number of modules you may wire in series is bounded by the inverter's tracking voltage window — the range of DC voltage over which the inverter can hold the maximum power point (MPPT — maximum power point tracking). That window is a property of the machine, and the application reads it from the inverter file. With no inverter file loaded there is no window, and therefore nothing to size a string against.
This is why the module file and the inverter file are usually loaded together at the start of a session, and why the question about calculating modules in series automatically leads back here. See Automatic string sizing.
Where to go next
Automatic string sizing
How many modules go in series, and the three limits that decide it
Cable routing
How DC, AC and medium-voltage runs are traced, and what trench lengths mean
Control rooms
How the ICR block capacity sets the number and position of control rooms
Simulation with AC capacity
Sizing the plant from a target AC capacity and DC/AC ratio instead