Sizing from an AC capacity
Work backwards from a contracted AC capacity and a target DC/AC ratio to a layout capped at the capacity you are allowed to build.
The normal way round is to fill the site: place as many modules as the usable area holds and read the resulting capacity off the plant chips. π Simulation with AC Capacity works the other way. You state the AC capacity you are contracted for and the DC/AC ratio you want to build at, and the plant is sized to match it.
Use it when a connection agreement fixes the megawatts you may export, and the design question is not how much the site could hold but how much of it to use.
Where it is, and what it needs
The button is the first of five in the Studies card on the Tools tab: π Simulation with AC Capacity, π€ Robotic Module Cleaning, Robot count from DXFβ¦, π Shadow View (row spacing) and β‘ Earthing Design. The card is there from the start, but every button except Robot count from DXFβ¦ is greyed out until a layout exists. The simulation works from a placed layout, because it needs to know what the site can deliver before it can cap anything to a target.

It also needs two files, because typed module dimensions carry no electrical data:
Generate a layout first
Let the site fill. That first run tells you the ceiling β the most DC the usable area will take on your current settings β which is the number every target is compared against.
Load a module file
The string sizing needs the module's voltages, which come from the .PAN file
rather than from the three dimension fields. Load .PAN is on the Array
tab β see Module specifications.
Load an inverter file
The inverter's rated AC output, its current limit and its DC power limit all
come from the .OND file. Load .OND is on the Electrical tab β see
Inverters.
Without both files the button answers with a message instead of the window: "Load a PAN module file and an OND inverter file first (in the input panel), then run the AC-capacity simulation."
The window
Simulation with AC Capacity is one window: inputs on the left, a live result on the right, and the action in the footer. Everything on the right updates as you type.

The strip
Across the top, the ceiling and the design: This layout holds x MWp DC Β· the target cannot exceed it, then chips reading String inverter or Central inverter and the table configuration as "n-string tables". The first number is the placed DC capacity of the layout you generated, and nothing in this window can raise it.
TARGET
| Field | Default | Range | What it does |
|---|---|---|---|
| AC capacity (kW) | The largest multiple of 100 kW that the layout holds at a ratio of 1.30 | 1.0β5,000,000 | The AC capacity you are sizing to. The equivalent in MW is shown beside it |
| DC/AC ratio | 1.30 | 0.80β2.50 | Installed DC divided by installed AC β the ratio you intend to build at |
| Overload limit | 1.5 in a string design, 1.4 in a central design | 1.00β2.00 | The design overload limit: the highest DC/AC ratio the window will size at. This is a design figure, not the inverter's nameplate DC input |
| Modules per string | The Array tab's Modules per row (fixed tilt) or Modules per string (NβS) (tracker) | 1β200 | The string length. Sizeβ¦ beside it opens the string-sizing window β see String sizing |
The AC capacity default is worked out from the first run's DC capacity: that DC divided by 1.30, rounded down to a whole 100 kW, so the window opens on Fits this layout. It is a starting point, not a suggestion β type the capacity you are contracted for over it.
EQUIPMENT
Two rows, MODULE · PAN and INVERTER · OND, each with a one-line specification of the loaded file and View and Replace⦠buttons, so you can check or swap either file without leaving the window. Under them an expander, Override nameplate values, exposes Module Pmax in W and Inverter rated AC in kW for the case where the file's figures are not the ones you are contracting against.
RESULT Β· updates as you type
A verdict banner states whether the target fits, and below it Target DC and Headroom sit over a capacity meter marked "layout holds x MWp", so you can see at once how much of the placed plant the target uses. Six tiles carry the sizing:
| Tile | What it reports |
|---|---|
| Inverters | The whole number of inverters the target needs |
| Strings per inverter | Parallel strings per inverter, from the inverter's own limits |
| Installed AC | Inverter count Γ rated AC output, always at or above the target, with "requested x MW" under it |
| Target DC | Requested AC Γ the DC/AC ratio |
| DC/AC ratio | The ratio the figures are built at |
| DC per inverter | The DC behind each inverter at that sizing |
Under the tiles sit two more inputs that belong to the result rather than the target:
| Field | Default | Range | What it does |
|---|---|---|---|
| ICR block AC (kW) | 0, shown as Not set | 0β5,000,000 | The AC capacity one ICR block serves. Beside it the window answers "β n blocks of x.xxx MWp DC"; while it is not set, "keeps the input panel's x MWp blocks"; with invalid inputs, β. See ICR blocks from an AC capacity |
| Strings per SMB | 20 | 1β500 | Central-inverter designs only. See Central inverters |

The verdicts:
| Verdict | What it means | What the window offers |
|---|---|---|
| Fits this layout | "Target DC uses n % of the x MWp placed. Regenerating trims the layout to y MWp." β the site can deliver it | The primary button in the footer |
| Needs x MWp more than this layout holds | The first run already used all the usable area there is | "β¦ Lower the target, or make room in the layout (tighter pitch, more area) and generate again.", with fix buttons Set AC capacity to β¦ kW and Set ratio to β¦ |
| DC/AC ratio is over the inverter's limit | "You asked for r; the overload limit is m. DC beyond the limit is clipped. Figures below use the limit." | Set ratio to β¦ and Raise limit to β¦ |
| Missing input | "Module Pmax and modules-per-string are required." or "Inverter rated AC power (Pac_rated) is required." | Fill the field, or the matching value under Override nameplate values |
If the layout was saved while capped, by an earlier version, its uncapped DC may
not be recorded. The strip then reads "This layout's full DC is not known",
the verdict reads This layout's full DC is not known, Headroom reads β, and
the primary button is greyed with "The layout's full DC is not known." The figures
are right; whether they fit the layout cannot be checked.
The footer
A tick box, Let me choose where placement starts β "After regenerating, click a point on the plot; the tables nearest it are kept." β then Close and the primary button. When the target fits, the button reads Regenerate layout at x.xx MWp and names the capacity it will trim the layout to. Otherwise it reads Regenerate layout, greyed out, and a line beside Close gives the reason:
| Verdict | Reason shown |
|---|---|
| Missing input | "Complete the inputs first." |
| DC/AC ratio is over the inverter's limit | "Lower the ratio or raise the limit." |
| Needs x MWp more than this layout holds | "Target DC exceeds the layout." |
How it sizes
The string geometry comes first, then the inverter count, then the DC target.
Modules in series are worked out by the same string sizing method used elsewhere in the application β the module's voltage behaviour at the site's temperature extremes against the inverter's voltage window. See String sizing.
Parallel strings per inverter come from the inverter's own limits: its input current limit and its DC power limit, whichever binds first β rounded to whole tables in a string-inverter design.
The inverter count follows from the target:
num_inverters = ceil( AC_capacity / Pac_rated )
installed_ac = num_inverters Γ Pac_rated β₯ AC_capacity| Term | What it is |
|---|---|
AC_capacity | The AC capacity you entered |
Pac_rated | The rated AC output of one inverter, read from the inverter file β or Inverter rated AC under the override expander |
ceil( β¦ ) | Rounded up to a whole inverter. There is no such thing as a fraction of an inverter |
num_inverters | The Inverters tile |
installed_ac | The Installed AC tile β the inverter count multiplied by the rated output |
Rounding up is the important behaviour: it never under-sizes. The installed AC capacity is always at or above your target, never below it. Where the inverter rating does not divide the target exactly you get the next whole inverter and a slightly higher installed figure β deliberately, because the alternative is a plant that cannot deliver what it was contracted for.
The target DC is then the requested AC capacity multiplied by the DC/AC ratio: the Target DC tile, and the figure in the primary button's label.
On a string plant the count is a floor for the plant. On a central plant it is the count exactly; see the next section.
Central inverters
On a central-inverter design the AC sets the inverters and the SMBs follow. With the
simulation on, the central inverter count is ceil(AC capacity Γ· rated AC) exactly,
not derived from the SMBs.
Strings per SMB (default 20, range 1β500) sizes the SMBs for the target DC, and they are shared evenly between the inverters. The window answers beside the field: "β 12β13 SMBs per inverter DC/AC up to 1.319", or, when the busiest inverter would go over the Overload limit, "β DC/AC up to x > limit" in warning colour. It is a warning, never a refusal; lower the DC/AC ratio or the strings per SMB, or raise the limit.
ICR block AC also decides how the inverters split between the blocks. A full ICR takes as many inverters as fit in the block AC, rounded down; full ICRs come first and the rest go in the last. Without a block AC the inverters are spread evenly. The answer beside the field reads:
"β n blocks of x MWp DC Β· f inverters, y MW each Β· split inverters"
with the split in a form like 10 Γ 3 + 2: ten ICRs of three and one of two. If the
blocks hold fewer inverters than the count, the blocks are counted from the split:
"β m blocks (f inverters, y MW each) Β· split inverters".
For example, 100,000 kW of 3,200 kW inverters at a ratio of 1.3, with 28 modules of
580 W to a string and a block AC of 12,500 kW, gives 32 inverters, 102.4 MW installed,
a 130 MWp target and blocks of 16.25 MWp. Each full ICR takes three inverters, and the
split is 10 Γ 3 + 2, so 11 ICRs. At 20 strings to an SMB that is 401 SMBs for 8,005
strings, 12β13 per inverter, DC/AC up to 1.319.
After a regeneration, Max SMB per Central Inverter on the Electrical tab holds the busiest inverter's SMBs and is greyed, with the hint "Set by the AC simulation: the busiest inverter's SMBs. The inverter count comes from the plant AC." See Inverters. An inverter over the overload limit is reported by the design checks, and never adds another inverter.
DC overload and the DC/AC ratio
The DC/AC ratio is installed DC capacity divided by installed AC capacity. A ratio of 1.4 means 1.4 MWp of modules behind every 1 MW of inverter. The window ships at 1.30.
| Inverter design | Shipped overload limit |
|---|---|
| String inverters | 1.5 |
| Central inverters | 1.4 |
Both figures are the design overload limit, and the Overload limit field lets you change them.
Why a ratio above 1 is normal
An array almost never produces its nameplate DC output. Nameplate is measured at standard test conditions, STC, and a real array is hotter than the STC cell temperature whenever irradiance is high, and below the STC irradiance level for most of the hours it generates at all. The result is that an inverter sized one to one with the array sits well below its rating for nearly all of the year.
Deliberately fitting more DC than the inverter can pass fills that gap. The array reaches the inverter's limit more often and for longer, the inverter runs nearer its efficient operating region, and on the handful of hours when the array would exceed the limit the inverter clips the surplus β it holds its output at the rating and the extra DC is not converted.
The Overload limit is the design overload figure, not the inverter's nameplate maximum DC input. Do not read 1.5 as a hardware rating you can push to. Check the manufacturer's own maximum DC input power and voltage before raising the field. Ask for a ratio above the limit and the window says so, sizes at the limit, and offers to set the ratio down or the limit up.
The two outcomes
Once the target DC is known, it is compared against what the first layout actually placed β the figure in the strip.
The target is at or below what the layout holds
The verdict reads Fits this layout. Click Regenerate layout at x.xx MWp and the layout is rebuilt capped to the target: the same site, the same settings, with placement trimmed so the installed DC capacity lands on your target instead of filling the ground. Tick Let me choose where placement starts first if you want to decide which end of the site keeps its tables: after the regeneration you click a point on the plot, and the tables nearest it are the ones kept.
This is the normal path. The capped layout is the one to review, export and issue, because it is the plant matching the connection you hold. The status line after the regeneration confirms it: "β¦ | DC target x MWp met".
The target is above what the layout holds
The verdict reads Needs x MWp more than this layout holds, and no regeneration can change that β the first run already used all the usable area there is. The window offers to set the AC capacity or the ratio down to what fits.
Before accepting either, check whether the site is really the binding constraint. The usable area is the boundary shrunk by the perimeter road width, with obstructions, corridors and terrain exclusions subtracted, so a target that misses by a little may be reachable through the layout inputs rather than the commercial ones β a narrower perimeter road, half tables enabled, or Maximize placement on an awkward boundary. See Maximize placement and half tables. Change those, generate again, and reopen the window.
If a regenerated plant lands below its target, the status line says so rather than leaving you to spot it on the plot: "β DC x MWp is BELOW the y MWp target β the site has no room left; reduce the AC capacity or DC/AC ratio".
ICR blocks from an AC capacity
The number of inverter control rooms follows the ICR Block field on the Site tab β the DC capacity one room serves; see Site parameters. When the connection is specified in AC per block rather than DC, enter that figure in ICR block AC and let the window convert it:
ICR block DC = ICR block AC Γ DC/AC ratio
ICR blocks = AC capacity Γ· ICR block AC, rounded up (at least 1)When the ratio is over the overload limit, the limit is used in its place, as it is everywhere else in the window. The answer beside the field shows both results before you commit to anything.
Regenerate writes the block DC into the ICR Block field, rounded up to three decimals so that a block is never smaller than the calculation β 12,500 kW Γ 1.325 = 16.5625 MWp becomes 16.563 MWp β and held within the field's own range of 0.1β500 MWp. The change is reported while the layout rebuilds, in the form "ICR block <old> MWp β <new> MWp", and again on the status line after the run as "| Input panel updated from the AC simulation: β¦". Leave ICR block AC at Not set and the field is left as it is.
In a capped layout the control rooms are counted against the DC target, not against the trimmed plant, and each is placed at the ICR length and width you set on the Structures & Shadow card. See Inverter control rooms for how rooms are counted and sited, and ICR blocks for what a block contains.
Why a capped plant has empty ground
A capped layout looks wrong at first sight. There is bare ground inside the fence that tables would obviously fit on, and the instinct is that the trim overshot. It did not, and the behaviour is worth understanding before you explain the drawing to anyone else.
The delivered DC must land at or just above the target, never below. If the trim undershot, the installed DC would be less than the ratio you designed to, and the delivered DC/AC ratio would fall short of the figure the whole exercise was built around. Landing slightly high is a rounding artefact; landing low is a failure to deliver the design.
Trimmed tables are held back and returned afterwards. The stages that run after placement clear more ground: control rooms are re-placed against the reduced capacity, lightning arresters clear the tables under their piles and shadows, inverter pads take theirs. Ground that was occupied when the trim was calculated may be free by the time those stages finish. So the trimmed tables are kept in reserve and put back after them, and any whose ground has since been taken by other equipment is skipped.
Half units are weighted by the modules they hold. The trim counts each table at its own modules, so a plant using half tables lands on the target just as one without them does.
The consequence: the empty ground on a capped plant is deliberate. It is the capacity you chose not to build.
Where the result appears
The Capacity group of the Summary view's Plant sheet carries the outcome:
| Row | What it reports |
|---|---|
| Plant AC capacity (MWac) | The AC capacity you typed, shared by units while the cap is on |
| DC / AC ratio | DC capacity over the plant AC |
| Inverter AC capacity (MW) | The installed inverter capacity. Shown only when it differs from the plant AC |
| DC / AC on inverters | DC capacity over the installed inverter AC. Shown with the row above |
Read them together, and read them against the target you typed. DC / AC ratio is the check that matters: it is the delivered ratio, computed from what was actually placed, and it is the figure that tells you the cap did what you asked. A delivered ratio marginally above the target is the expected result of landing DC just above target. The DC capacity chip under the view shows the capped figure. See Summary view for the full row set.
CUF on AC on the Energy view and the Summary is worked against the same plant AC. The capped layout carries into everything downstream unchanged: the deliverables package, the bill of materials and the energy calculation all describe the capped plant, so run the energy calculation again after a regeneration.
What the window keeps
The window reopens on the inputs it closed with, whether you closed it or
regenerated: AC capacity, DC/AC ratio, Overload limit, ICR block AC,
Modules per string, Module Pmax, Inverter rated AC, Let me choose where
placement starts, Strings per SMB, and a .PAN or .OND you loaded in the
window. Modules per string and the files come back only while the panel's are
unchanged; otherwise the panel's win.
The inputs are saved with the project, except a .PAN or .OND loaded only in this
window. Loading a new boundary file clears them.
Where it fits in the design sequence
Run an uncapped layout first
Let the site fill. That first run sets the figure in the window's strip β the most DC the usable area will take on your current settings.
Settle the layout inputs before capping
Perimeter road, obstructions, terrain, half tables, arresters: all of them move the ceiling. Capping to a target and then changing a layout input means the trim was calculated against a plant that no longer exists.
Size to the target
Enter the contracted AC capacity and the DC/AC ratio you intend to build at, and read the inverter count and target DC off the tiles.
Regenerate at the target
Click Regenerate layout at x.xx MWp and review the plot. The bare ground is expected; check DC / AC ratio on the Summary view rather than the appearance of the plan.
Calculate energy again, then export
Energy is computed from the placed capacity, so the figures from the uncapped run no longer apply. Re-run it before exporting anything.
Where to go next
Energy charts and time-series export
The hourly energy window with its daily and monthly views, which data source is behind it, and exporting a full-year generation series at your chosen interval.
Robotic cleaning fleet
Sizing the number of cleaning robots a plant needs, and deciding gap by gap where a supported bridge will be installed.