The Cables card on the Electrical tab — whether runs are routed and measured, how each cable class is laid, the DC allowances and the voltage-drop limits.

The Cables card decides whether the application routes and measures the cables between the tables, the inverters or string monitoring boxes (SMBs) and the control rooms, how each class of cable is laid, and what allowances are added to the DC string-cable total. It is the third card on the Electrical tab, after the inverter card and the ACCB & Transformer card (Transformer in a central-inverter design — see ACCB and transformers). Routing is off as shipped, because it is the slow step on a large plant. The equipment is placed and counted whether or not the cables are traced.

How the runs are routed once the option is on — the patterns, the trenches and the medium-voltage network — is on Cable routing. This page covers the card.

The Cables card at its defaults: Calculate cables unticked, the DC string, AC and MV cable laying selectors, inter-module lead 0.00 m/module, the string return run unticked, DC cable slack 10.0 %, and Advanced… for the voltage-drop limits.
The Cables card

The fields

FieldDefaultRangeWhat it does
Calculate cablesoff—Routes every run on the next Generate Layout and reports the lengths
DC string cable layingBuried, in conduitor Buried directly · Above ground, in conduit on concrete blocksHow the DC string cables are laid
AC cable laying (string) / DC trunk laying (central)Buried directlyor Above ground, on concrete blocksHow the AC feeders or the DC trunks are laid
MV cable layingBuried directlyor On cable trayHow the medium-voltage cables are laid
Inter-module lead0.00 m/module0.00–2.00 m/moduleExtra string cable per module for the leads between modules, counted once per string. Fixed-tilt tables only
String return run along tableoff—Tick for daisy-chain wiring: adds one conductor's run back along the table per string. Fixed-tilt tables only
DC cable slack10.0 %0.0–30.0 %Slack and wastage added to the DC string-cable total, trackers included
DC trunk conductor (central)Aluminiumor CopperThe metal of the SMB-to-central-inverter cable
Voltage-drop limitsall at defaults—Advanced… opens the limits the cables are sized to

The tick, the laying choices, the conductor and the allowances are saved in the project file and come back when it is reopened. They are also inputs to the run: change any of them after generating and the layout is marked out of date until you generate again. See Out-of-date results.

Calculate cables

Off by default. With it off, the layout is generated, the inverters or monitoring boxes are placed and counted, and no cable is routed. With it on, the application traces every run on the next Generate Layout and reports its length.

What gets traced depends on the design, because the conversion happens in a different place:

RunFromTo
String DC cableEach table (MMS)Its string inverter
AC cableEach string inverterIts ICR

The inverter converts in the field, so the run into the control room is AC. The totals appear on the String DC cable (m) and AC cable to ICR (m) rows of the Summary view.

Medium-voltage runs from the control rooms to the main control room are routed in both designs, once a main control room has been placed and the layout generated again with this option on. With the grid connection by others they run to the handover point instead, when there is one.

The performance notice

Ticking the box raises Cable Calculation — Performance Notice before anything is enabled. It reads: Cable calculation can take a long time on large or complex layouts. — It is recommended to generate the plant layout first without cable calculation, review the result, and then enable cable calculation for the final run. Do you want to enable cable calculation now?

The Cable Calculation — Performance Notice with its text and the Enable Now and Not Now (Recommended) buttons.
The performance notice
ButtonWhat it does
Enable NowLeaves the box ticked. Cables are routed on the next Generate Layout
Not Now (Recommended)The default. Unticks the box again

Opening a saved project that had the option on does not raise the notice.

The Cables card with Calculate cables ticked and the laying selectors and allowances below it.
Cable calculation switched on

Take the recommendation on a plant you have not laid out before. Cable routing is the slow step on a large plant, and it is the step whose result you are least likely to keep: change the table configuration, the perimeter road, the ICR block or the strings per inverter, and every run is traced again from scratch.

What you still get with cables off

  • The inverter and monitoring box counts are computed anyway. So are their loads, the central inverter count, and everything downstream that depends on them — the AC capacity, the DC / AC ratio, the single-line diagram and the bill of materials.
  • The cable rows of the Summary view read needs Calculate cables, as a link to this card.
  • The cable rows of the Layers popover stay disabled.
  • The design check C-06 Cables computed stays open, and the checks that read the cables say what they need. See Design checks.

One more run with the box ticked fills in the cable numbers.

How each cable class is laid

The three laying fields decide what each class needs beside the cable, and whether it counts as trench. A plot records the laying it was routed with, so changing a field alone changes nothing until the next Generate Layout.

ClassOptionWhat it means
DC stringBuried, in conduitEach DC route's cables in one 40 mm HDPE conduit, in a trench
Buried directlyIn a trench, no conduit
Above ground, in conduit on concrete blocksIn the conduit, on concrete blocks; no trench
AC feeder or DC trunkBuried directlyIn a trench
Above ground, on concrete blocksOn concrete blocks, clamped; no trench
MVBuried directlyIn a trench
On cable trayNo trench; the BOM measures the tray along the MV route

Only buried classes count as trench. The Summary view's trench row for a class laid above ground reads laid above ground, and for MV on a tray on cable tray. The bill of materials follows: conduit and its fittings, concrete blocks, clamps and tray appear with the laying that needs them. See Bill of materials.

The three DC allowances

The routed length of a string cable is the distance from the table to the inverter or monitoring box. Three further figures turn that into a quantity you can order against, and they are added to the DC string-cable total only.

Inter-module lead

Inter-module lead is extra string cable allowed per module for the leads that join one module to the next, counted once per string. It ships at 0.00 m per module, because the module supplier normally provides these leads with the modules. Enter a figure only when your procurement buys that cable separately. It applies to fixed-tilt tables only.

String return run along table

How much string cable a table needs depends on how its strings are wired.

WiringThe string's two leadsSetting
LeapfrogExit at the same end of the tableLeave String return run along table unticked — the default
Daisy-chainEnd at opposite ends of the table, so one conductor must run back along the table to exit beside the otherTick String return run along table, and that run back along the table is added per string

It applies to fixed-tilt tables only.

DC cable slack

DC cable slack is the slack and wastage added to the DC string-cable total, as a percentage. It ships at 10 %, the bill-of-quantity convention. Unlike the other two allowances it applies to every design, tracker plants included.

DC trunk conductor

Central-inverter design only. The trunk from each SMB to its central inverter is sized in the metal you choose, by voltage drop and current-carrying capacity, as two single-core conductors. On one sample plant the same trunk came out at 150 mm² in aluminium and 120 mm² in copper. The lugs in the bill of materials follow the metal: DC cable lug, bimetallic for aluminium, Cable lug, copper for copper. The string cables are copper either way.

Voltage-drop limits

The limits the cables are sized to are Advanced settings, not fields on this card. The row shows all at defaults or how many are changed, and Advanced… opens them.

SettingDefaultWhat it limits
DC string voltage drop1.5 %The DC string cables; design check E-08
LV feeder drop limit2.5 %Each inverter-to-ACCB feeder; design check E-02
MV voltage drop2.0 %The MV cables; design check E-02

Each inverter-to-ACCB feeder is one run of the plant's size A or size B. Size A is the smallest standard size whose derated current-carrying capacity carries the feeder's current; size B is the next one up. A feeder takes A unless its drop exceeds the limit, and there is never a third size or a second run. A feeder neither can serve is flagged in the schedules workbook and the checks. The current comes from the inverter file, or from the maximum strings × the string's power without one. The MV sizing uses the MV voltage on the ACCB & Transformer card.