Design checks
Every design check by ID — what it tests, the limit it uses, the link that fixes it, the sentences it writes and what to change to clear it.
The application runs 29 design checks on every generated layout, in three families: reconciliation (R), completeness (C) and engineering (E). A check never blocks anything. How to read and accept them is on the Checks view.
A limit below is an Advanced setting under Checks and limits, shown at its default. Each row's title is the application's own.
Reconciliation
Two figures for the same thing must agree. None of these has a Fix link or can be accepted: the row carries the note "No setting changes this: send us the project". If one fails, send the project file to SolarLayout.
| ID | Title | Compares | Limit |
|---|---|---|---|
| R-01 | Modules = Σ tables × modules per table | The layout's module count against each table's modules, summed | |
| R-02 | Strings agree: per inverter = per table | Each inverter's strings, from its capacity, against the strings on its tables | |
| R-03 | Block quantities sum to the plant | Every table, module and string in exactly one ICR block | |
| R-04 | S1 cable totals = takeoff | Each cable class's metres in the schedules workbook against the quantities | ± 0.5 % |
| R-05 | Land account closes | Gross site less every exclusion, booked in order, against the usable land | ± 0.01 ha |
| R-06 | Drawn trench = scheduled | The trench the drawings show against the trench the quantities book | ± 0.5 % |
| R-07 | SLD counts and ratings = snapshot | The counts and ratings on the package's single-line diagram against those every other deliverable prints |
R-04 does not apply when there are no cable records, and R-06 does not apply when every cable class is above ground.
Completeness
What a package needs. A failing row reads "1 missing" or "9 missing".
| ID | Title | Passes when | Fix |
|---|---|---|---|
| C-01 | Location surveyed or confirmed | The site is surveyed, or placed by you in Site reference | Fix: Site tab |
| C-02 | Lightning protection designed | Lightning arresters are placed (Place Lightning Arresters on the Site tab) | Fix: Site tab |
| C-03 | MV collection designed | An MCR or a USS is placed, or the grid connection is set to By others. By others, it passes with a handover point and does not apply without one | Fix: Tools tab |
| C-04 | Module and inverter from datasheets | The module's PAN and the inverter's OND file are loaded | Fix: Array tab; Fix: Electrical tab when only the OND is missing |
| C-05 | Project and title-block fields complete | Company name, Company logo, Drawing-number pattern, Project name, Project code, Client, Location, Drawn by, Checked by and Approved by are all filled | Fix: Project details |
| C-06 | Cables computed | Calculate cables is on, and the layout generated | Fix: Electrical tab |
| C-07 | Pile pattern defined | A pile pattern exists | Fix: Piles |
Engineering
| ID | Title | Tests | Limit | Fix |
|---|---|---|---|---|
| E-01 | IDT loading | Each inverter duty transformer's load against its standard rating | 100 % | Fix: Electrical tab |
| E-02 | LV feeder drop and MV drop | Inverter-to-ACCB feeders against the feeder limit and the plant's current-weighted budget, and MV runs against theirs | 2.5 %, 1.5 %, 2.0 % | Fix: Electrical tab |
| E-03 | Inverter DC:AC band | Each inverter's DC:AC against the plant's own ratio | ± 15 % | Fix: Electrical tab |
| E-04 | String voltage window | Done by hand; always reads can't check | ||
| E-05 | Shading window | Done by hand; always reads can't check | ||
| E-06 | ICR inverter count | The devices each ICR carries against its rating, the design's own cap | Fix: Site tab | |
| E-07 | Trenches inside the plant, not under tables | Feeder and trunk trenches that could not be kept inside the plant or clear of the tables | 0 runs | Fix: Sketch Mode |
| E-08 | DC string drop | Every DC string, table to its inverter, as the cable schedule sizes it | 1.5 % | Fix: Electrical tab |
| E-09 | Tables inside arrester cover | Every corner of every table within an arrester's protection radius | 0 tables | Fix: Site tab |
| E-10 | Clearances | Every table inside the boundary setback (the perimeter road) and clear of every transmission-line corridor | Fix: Site tab | |
| E-11 | Every block's ICR placed | The ICRs each plot needs against those that found room | Fix: Site tab | |
| E-12 | DC trunks buildable | Each DC trunk's drop, as parallel runs of the largest conductor. Central-inverter designs only | 2 runs | Fix: Electrical tab |
| E-13 | Building shadows cleared | Tables in the year-round shadow of the ICRs and other buildings removed, from the site's latitude | Fix: Site tab | |
| E-14 | Central inverter DC/AC | Each central inverter's DC against the AC simulation's overload limit. Central-inverter designs that ran the simulation only | The simulation's limit | Fix: Tools tab |
| E-15 | Transformer forms | Each transformer against the allowed forms: every LV winding carries an ACCB, or an inverter on a central design | Fix: Electrical tab |
When a check can't run
| The row says | What to do |
|---|---|
| "Load the inverter file (OND) for the IDT loads." (E-01) | Load the OND file on the Electrical tab, and generate |
| "Load the inverter file (OND) for the inverters' AC rating." (E-03) | As above |
| "The cables are not routed. Turn on Calculate cables and generate the layout." (E-02, E-08, E-12) | Tick Calculate cables, and generate |
| "No lightning arresters are placed (C-02)." (E-09) | Tick Place Lightning Arresters on the Site tab, and generate |
| "Not checked in this version: … by hand." (E-04, E-05) | Do the check yourself, then accept it |
When a check does not apply
- E-12: "A string-inverter plant has no DC trunks."
- E-14: "A string-inverter plant has no central inverters.", or "Without an AC-capacity simulation the central inverters are counted from the SMBs, and no DC/AC limit applies."
What a finding says
The application writes each finding with your design's figures. The examples show the wording. On a multi-plot site the plot's name leads the sentence, and in a central-inverter design the wording follows the equipment: SMBs for inverters, DC trunk trenches for AC trenches.
| Check | Sentence |
|---|---|
| E-02 | "5 AC feeders drop more than 2.5 % (worst 2.98 %): 321–372 m (longest: ICR3-INV-42)." |
| E-02 | "1 AC feeder carries 812 A, more than one 630 mm² run can." |
| E-02 | "The plant's LV AC drop averages 1.56 %, over the 1.5 % budget." |
| E-06 | "ICR 3 carries 60 inverters; it is rated for 53." With several: "4 ICRs carry more inverters than their rating of 53: ICR 2 (60), ICR 4 (58), …" |
| E-07 | "1 AC trench runs outside the plant boundary; it keeps its original route in the drawing, the DXF and the quantities." |
| E-07 | "2 AC trenches still run under a table." |
| E-08 | "3 DC string runs drop more than 1.5 % (worst 1.82 %)." |
| E-11 | "2 of the 6 ICRs this plot needs found no room in it." |
| E-12 | "1 DC trunk is too long for 1.5 % drop even as 2 parallel 630 mm² runs: …", ending with the SMB and the length |
| E-13 | "Building-shadow clearance skipped: the site has no latitude, so tables in the shadow of the ICRs and other buildings were not removed." |
| E-14 | "3 of the 20 central inverters carry more DC than the 1.40 DC/AC limit (worst 1.46, ICR 2). Lower the DC/AC ratio or the strings per SMB, size the ICR blocks by AC, or raise the overload limit." |
| E-15 | "ICR 2: 3 ACCBs on a 5-winding transformer, 1 LV winding spare. Add a 4-winding form or change the block." |
Clearing a finding
A check clears when its result passes. An input that makes the layout out of date needs a regenerate before you read the result again. An edit on the ACCB & Transformer card and a limit with the pill Checks · applies now need no Generate. What to look at:
| Check | What to look at |
|---|---|
| E-01 | A transformer whose load fits no listed rating at or under the size limit has no rating, and fails. Look at Standard transformer ratings (kVA):, Transformer size limit: and the forms on the ACCB & Transformer card (Transformer on a central design). See ACCBs and transformers |
| E-02 | A feeder over its drop, or the plant's drop over budget: shorter runs. A smaller ICR Block gives more ICRs, each nearer the inverters it serves. A feeder "more than one 630 mm² run can" carry is about the inverter's current, so its length doesn't change that finding. A limit you have agreed otherwise goes in Advanced settings under Limits… |
| E-03 | The inverters on the row's Affects line, and the inverter card on the Electrical tab. See Inverter |
| E-06 | The number of ICRs and each one's rating both follow ICR Block on the Site tab. See Inverter control rooms |
| E-07 | Switch on the AC cables layer (DC trunks in a central design) and find the run. In Sketch Mode, move the ICR it serves, which routes the cables again. See Cable routing |
| E-08 | With a Y harness, Y pair cable size and String cable size in Advanced settings, under Cables: a Y pair keeps its size whatever its drop. A string on its own is already sized to stay within the limit |
| E-09 | LA protection radius on the Site tab. Placement covers each table's centre, and the check reads every corner, so tables at the edge of a circle can show here. See Lightning arresters |
| E-10 | Perimeter road width and Line corridor (each side) on the Site tab, and the tables on the row's Affects line |
| E-11 | Each ICR must fit entirely inside the usable area at the ICR length and width in Structures & Shadow. A smaller footprint is easier to place, and a larger ICR Block asks the plot for fewer rooms |
| E-12 | A trunk's drop follows its length, its current and its conductor. Shorter runs, as for E-02; fewer strings per SMB; or DC trunk conductor on the Cables card, since copper drops less than aluminium. A limit you have agreed otherwise goes in DC trunk parallel runs, under Limits… |
| E-13 | Pick the boundary file again and give the site its location or latitude in Site reference |
| E-14 | The finding's own sentence names the levers. See Sizing from an AC capacity |
| E-15 | Add the form the finding names on the card, or change the block |
In the BOM view
A failed check's sentence appears as "Check: <ID> · <sentence>" on the lines it concerns, in the BOM view only, never in a file:
| Finding | Line |
|---|---|
| ICR over its rating or not placed | The ICR building |
| Central inverter over its limit | Central inverter |
| Spare transformer winding | Inverter duty transformer |
| AC feeder over its limit, over one run, or the plant's drop over budget | LV AC cable |
| DC trunk too long | DC trunk cable |
| DC string drop | DC solar cable |
| Building shadows skipped | PV module |
Where to go next
Summary view
Every row of the Summary view — the Plant and By block sheets, what stands above them, the reasons in place of a figure, and How?
Shortcuts and commands
Every keyboard shortcut and gesture, the typed command line in Sketch Mode, the ribbon, the tools row of each view, the Export menu, the SLD and BOM panels, and the full menu map.