Line reference
Every entry in the built-in BOM profile, by category, with its unit, how it is counted and when it applies, and what feeds the quantities.
This page lists every entry in SolarLayout standard, the built-in BOM profile, in the order of the BOM view. An entry gives a line when it applies to your design and the layout has something to count. A company or client profile starts from this list and changes or adds to it.
Reading the tables
How it is counted:
| Wording | Meaning | Source in the BOM view |
|---|---|---|
| Measured | Counted or measured from the design | Measured |
| A number per something | That factor times the count. Change it in Factor | Rule |
| Factor you enter | The rule is set and the factor is blank, so the line starts as ! Needs factor | Rule |
| You enter it | The line starts as ! Needs quantity | Manual |
When and how:
| Wording | Meaning |
|---|---|
| — | Applies to every design, with a line whenever the layout has any to count |
| A design condition | The entry applies only then. Otherwise it is under Not for this design on the Profile card |
| Works | Installation or civil work rather than a supply item |
| Spare | The allowance follows Spare for discrete consumables, 5 % by default |
| Off by default | Listed under Switched off on the Profile card, with no line in the BOM |
Units are as the application prints them: Nos, set, m, t, m³, LS (lump sum) and MWp. The abbreviations used are MMS (module mounting structure), SMB (string monitoring box), ACCB (AC combiner box), ICR (inverter control room), IDT (inverter duty transformer), MCR (main control room) and USS (unit substation).
PV modules
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| PV module | Nos | Measured | — |
Inverters & DC collection
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| String inverter | Nos | Measured | String inverter plants |
| Central inverter | Nos | Measured | Central inverter plants |
| String monitoring box (SMB) | Nos | Measured | Central inverter plants |
| Inverter mounting stand | Nos | 1 per string inverter | String inverter plants |
Structure & foundations
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| MMS table (supply package) | Nos | Measured | Fixed tilt |
| Module mounting structure steel | t | Factor you enter, kg per table | Fixed tilt · Off by default |
| Tracker (supply package) | set | Measured | Trackers |
| MMS pile | Nos | Measured | Fixed tilt |
| MMS pile · tracker posts, when not in the OEM's package | Nos | Measured | Trackers · Off by default |
| Tracker control system | LS | Measured | Trackers |
| Module mounting bolt set | set | 4 per module | Spare · Off by default |
| Module earthing washer | Nos | 4 per module | Spare · Off by default |
| MMS fasteners | t | Factor you enter, kg per table | Fixed tilt · Off by default |
DC cabling & connectors
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| DC solar cable | m | Measured | — |
| DC connector, male | Nos | 1 per string | Spare |
| DC connector, female | Nos | 1 per string | Spare |
| DC connector set with inline fuse | set | 1 per string | String fuses inline, or inline and inside the device · Spare |
| Y connector set | set | 1 per string pair | Y harness, with string fuses inside the device or none · Spare |
| Y connector set with fused arms | set | 1 per string pair | Y harness, with string fuses inline, or inline and inside the device · Spare |
| DC trunk cable (SMB → central inverter) | m | Measured | Central inverter plants |
| Cable gland, single compression | Nos | 1 per conductor end | Central inverter plants · Spare |
| Cable lug, copper | Nos | 1 per conductor end | Central inverter plants · Spare |
| DC cable lug, bimetallic | Nos | 1 per conductor end | Central inverter plants · Spare |
| HDPE DWC conduit · for DC cables | m | Measured | DC string cable in conduit, buried or above ground |
| Cable tie · DC cable along the tables and trackers | Nos | Measured | Spare |
| Conduit fitting · coupler | Nos | You enter it | DC string cable in conduit, buried or above ground · Spare |
| Conduit fitting · T joint | Nos | You enter it | DC string cable in conduit, buried or above ground · Spare |
| Conduit fitting · L joint | Nos | You enter it | DC string cable in conduit, buried or above ground · Spare |
| Conduit fitting · 3-way | Nos | You enter it | DC string cable in conduit, buried or above ground · Spare |
| Conduit fitting · 4-way | Nos | You enter it | DC string cable in conduit, buried or above ground · Spare |
| UPVC clamp · above-ground laying | Nos | Measured | DC string cable above ground · Spare |
| UPVC clamp · above-ground laying of LV AC cable | Nos | Measured | AC cable above ground · Spare |
LV AC system
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| AC combiner box (ACCB) | Nos | Measured | String inverter plants |
| LV AC cable | m | Measured | String inverter plants |
| Cable gland | Nos | 1 per cable end | String inverter plants · Spare |
| Cable lug, bimetallic · source end | Nos | 3 per source-end cable end | String inverter plants · Spare |
| Cable lug, aluminium · receiving end | Nos | 3 per receiving-end cable end | String inverter plants · Spare |
| LV AC cable · ACCB / central inverter → transformer | m | Measured | — |
| Cable gland · ACCB / central inverter → transformer | Nos | 1 per cable end | Spare |
| Cable lug, bimetallic · ACCB / central inverter → transformer, at the ACCB / inverter | Nos | 3 per source-end cable end | Spare |
| Cable lug, aluminium · ACCB / central inverter → transformer, at the transformer | Nos | 3 per receiving-end cable end | Spare |
| Ladder cable tray · at the ICR | m | Factor you enter, per ICR | — |
| Cable tray canopy and support · at the ICR | m | Factor you enter, per ICR | — |
| Ladder cable tray · for MV cable | m | Measured | MV cable on cable tray |
MV system
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Inverter duty transformer | Nos | Measured | — |
| MV cable | m | Measured | — |
| MV termination kit · at the IDT | Nos | 1 per cable end | — |
| MV termination kit · at the MCR | Nos | 1 per cable end | Grid connection on this site |
| MV termination kit · at the handover point | Nos | 1 per cable end | Grid connection by others |
| Power transformer | Nos | Measured | — |
| MV breaker panel (ICOG) | Nos | 1 per ICR | — |
| HT panel · at the MCR | Nos | 1 per MCR | — |
| HT panel · at a USS | Nos | 1 per USS | — |
| HT feeder panel · for the auxiliary transformer | Nos | 1 per MCR | — |
| MV straight-through joint kit | Nos | 1 per joint | — |
| Metering yard | set | You enter it | — |
Earthing & lightning protection
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Lightning arrester, ESE | Nos | Measured | — |
| Earth pit · for arresters | Nos | Measured | — |
| Earthing strip · for arresters | m | 50 per arrester | — |
| Earthing cable · for string inverters | m | 15 per string inverter | String inverter plants |
| Earth pit · for string inverters | Nos | Measured | String inverter plants |
| Earth pit · for transformers (body) | Nos | Measured | — |
| Earth pit · for other equipment at the ICR | Nos | Measured | — |
| Earth pit · for other equipment at the MCR | Nos | Measured | — |
| Earth pit · for the USSs | Nos | Measured | — |
| Earth pit · to meet the plant grid target | Nos | Measured | — |
| Earth pit · for the fence, poles and other equipment | Nos | Measured | — |
| Earthing strip · main earthing ring | m | Measured | — |
| Earth pit · for the main earthing ring | Nos | Measured | — |
| Earthing strip · array mesh | m | Measured | — |
| Earthing strip · in the cable trenches | m | Measured | — |
| Earthing strip · round the ICRs, MCR and USSs | m | Measured | Grid connection on this site |
| Earthing strip · round the ICRs | m | Measured | Grid connection by others |
| Earthing strip · for the fence, poles and other equipment | m | Measured | — |
| Earthing strip · copper | m | You enter it | — |
| Earthing bolt set · array mesh jumpers | set | 2 per jumper or bridge | Spare |
| Earthing cable lug · for string inverters | Nos | 4 per string inverter | String inverter plants · Spare |
| Earthing cable · for central inverters | m | Factor you enter, per central inverter | Central inverter plants |
| Earthing cable lug · for central inverters | Nos | Factor you enter, per central inverter | Central inverter plants · Spare |
| Earthing cable · for SACU, PLC box and SMB | m | You enter it | — |
| Earthing cable lug · for SACU, PLC box and SMB | Nos | You enter it | Spare |
Communication, SCADA & security
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| SACU (smart array control unit) | Nos | 1 per ICR block | Power-line communication |
| CCTV system | set | You enter it | — |
| Weather monitoring station | set | 1 at the MCR | Grid connection on this site |
| Weather monitoring station · on site | set | 1 on site | Grid connection by others |
| PLC box | Nos | 1 per ICR | Power-line communication |
| RTU panel | set | 1 per ICR | — |
| Modem for remote monitoring | set | You enter it | — |
| RS485 cable | m | Measured | RS485 communication |
| RS485 cable · to the weather stations | m | 50 per weather station | — |
| CAT-6 cable | m | You enter it | — |
| Optical fibre cable | m | Measured | — |
| Conduit for communication cable | m | Measured | — |
| Conduit for communication cable · for the weather station links | m | 50 per weather station | — |
| Communication cable termination · RS485 | Nos | 8 per cable end (one per core of the 4-pair cable) | RS485 communication · Spare |
| Communication cable termination · RS485, to the weather stations | Nos | 16 per weather station (8 at each end) | Spare |
| Communication cable termination · CAT-6 | Nos | You enter it | Spare |
| Weather monitoring station · module temperature only | set | 1 per ICR | — |
Aux power & lighting
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Street light (perimeter) | set | Measured | — |
| ACDB panel | Nos | 1 per ICR | — |
| Auxiliary transformer · part of the ACCB panel | Nos | 1 per ICR | String inverter plants |
| Auxiliary transformer · part of the LT panel / ACDB | Nos | 1 per ICR | Central inverter plants |
| Auxiliary transformer · outdoor, fed by the HT feeder | Nos | 1 per MCR | — |
| UPS | Nos | 1 per ICR | — |
| Equipment-yard light · equipment yard | set | Factor you enter, per ICR | — |
| Aux power cable · 3C × 25 mm² Al | m | You enter it | — |
| Aux power cable · 4C × 10 mm² Cu | m | You enter it | — |
| Aux power cable · 4C × 16 mm² Al | m | You enter it | — |
| Aux power cable · 4C × 35 mm² Al | m | You enter it | — |
| Aux power cable · 2C × 4 mm² Cu | m | You enter it | — |
| Aux power cable · 2C × 2.5 mm² Cu | m | You enter it | — |
| Control cable · 19C × 1.5 mm² | m | You enter it | — |
| Control cable · NIFPS to ICOG panel | m | You enter it | — |
| Control cable · 2C × 1.5 mm² | m | You enter it | — |
| Gland for aux and control cable · 2C × 1.5 mm² | Nos | You enter it | Spare |
| Gland for aux and control cable · 19C × 1.5 mm² | Nos | You enter it | Spare |
| Gland for aux and control cable · 2C × 2.5 mm² | Nos | You enter it | Spare |
| Gland for aux and control cable · 2C × 4 mm² | Nos | You enter it | Spare |
| Gland for aux and control cable · 3C × 25 mm² | Nos | You enter it | Spare |
| Gland for aux and control cable · 4C × 10 mm² | Nos | You enter it | Spare |
| Gland for aux and control cable · 4C × 16 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · pin, 1.5 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · bimetallic pin, 2.5 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · bimetallic ring, 2.5 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · bimetallic pin, 4 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · bimetallic ring, 10 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · bimetallic ring, 16 mm² | Nos | You enter it | Spare |
| Lug for aux and control cable · bimetallic ring, 25 mm² | Nos | You enter it | Spare |
Civil works
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| ICR building | Nos | Measured | — |
| Fence · boundary | m | Measured | — |
| Gate · main | Nos | You enter it | — |
| Road · perimeter | m | Measured | Works · Off by default |
| Cable trench | m | Measured | Works · Off by default |
| Equipment foundation · for string inverters | Nos | 1 per string inverter | String inverter plants · Works · Off by default |
| Equipment foundation · for transformers | Nos | 1 per transformer | Works · Off by default |
| Hume pipe · road crossings | Nos | You enter it | — |
| MCR building | Nos | Measured | — |
| MCR furniture and air conditioning | set | You enter it | Grid connection on this site |
| MCR wiring and lighting | LS | You enter it | Grid connection on this site · Works · Off by default |
| Security cabin | set | You enter it | — |
| Fence · ICR yard | m | 120 per ICR | — |
| Gate · ICR yard | Nos | 2 per ICR | — |
| Gravel · ICR yard | m³ | 40 per ICR | — |
| Road · internal | m | You enter it | Works · Off by default |
| Road · approach | m | You enter it | Works · Off by default |
| Drain | m | You enter it | Works · Off by default |
| Concrete block for above-ground laying · DC conduit, above ground | Nos | Measured | DC string cable above ground |
| Concrete block for above-ground laying · LV AC cable, above ground | Nos | Measured | AC cable above ground |
| Concrete block for above-ground laying · DC trunk cable, above ground | Nos | Measured | DC trunk above ground |
| Equipment foundation · for central inverters | Nos | 1 per central inverter | Central inverter plants · Works · Off by default |
| Equipment foundation · for SMBs | Nos | 1 per SMB | Central inverter plants · Works · Off by default |
| Equipment foundation · for ACCBs | Nos | 1 per ACCB | String inverter plants · Works · Off by default |
| Equipment foundation · for ACDB panels | Nos | 1 per ICR | Works · Off by default |
| Equipment foundation · for ICOG panels | Nos | 1 per ICR | Works · Off by default |
| Equipment foundation · for NIFPS | Nos | 1 per IDT | Works · Off by default |
| Equipment foundation · for PLC boxes | Nos | 1 per ICR | Power-line communication · Works · Off by default |
| Equipment foundation · for the HT panel | Nos | 1 per HT panel | Works · Off by default |
Safety & fire
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Fire extinguisher | set | You enter it | — |
| Fire bucket stand | set | You enter it | — |
| First-aid box | Nos | You enter it | — |
| Danger and notice board | Nos | You enter it | — |
| Safety kit | set | You enter it | — |
| NIFPS (nitrogen injection fire protection) | set | 1 per transformer | — |
O&M & water
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Cleaning robot | Nos | Measured | Once a cleaning fleet is sized |
| Cleaning robot bridge | Nos | Measured | Once a cleaning fleet is sized |
| Water tank · module cleaning | set | You enter it | — |
| Water tank · MCR | set | You enter it | Grid connection on this site |
| Borewell and RO plant | set | You enter it | — |
Services
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Installation of structure and modules | MWp | Measured | Works · Off by default |
| Installation and commissioning, DC side | MWp | Measured | Works · Off by default |
| Cable termination works · communication cables | LS | You enter it | Works · Off by default |
Mandatory spares
| Item | Unit | How it is counted | When and how |
|---|---|---|---|
| Mandatory spares | LS | You enter it | — |
What feeds the lines
Most quantities come straight from the layout. These lines also read a design choice, so they are the ones that move when you change it.
Structure
The structure is bought as a package, not in parts.
- MMS table (supply package) has one line per table type, and its specification prints the table, module, tilt, clearance, wind and finish. For example: "2P × 28 portrait, full table (56 modules); module 2,380 × 1,130 mm, 580 Wp; tilt 8.4°; clearance 0.5 m; wind …; Hot-dip galvanised". It includes the structure, fasteners and module mounting hardware, as per the supplier's design.
- Tracker (supply package) includes the structure, posts, drive, controller and module mounting hardware, as per the OEM. It is not split into interior and perimeter trackers. Tracker control system is one lump sum.
- MMS pile needs a pile pattern. See Piles.
DC protection
These lines read the Isc from the PAN file, and Bifacial module and Max series fuse from the Array tab. The design Isc is the module's Isc, plus Bifacial current gain when the module is bifacial.
| Item | Rule |
|---|---|
| Inline string fuse | String fuse factor × design Isc, then the next listed size |
| SMB input fuse | String fuse factor × strings per input × design Isc, then the next listed size |
| DC disconnector | DC disconnector factor × the most strings on an SMB × design Isc, then the next listed size |
| SMB inputs | The most strings on an SMB. With a Y that pairs, the most inputs any SMB uses |
The Line card prints the working, such as "String fuse: 1.56 × 15.62 A = 24.3672 A → 25 A (Isc 14.2 A + 10 % bifacial)". Two warnings can appear, and neither changes the status: "The <item> needs <n> A, above the largest size in its list (<largest> A)." and "The <a> A string fuse is above the module's <b> A maximum series fuse." The size lists are BOM settings.
DC harness and string fuses
DC harness and String fuses on the Electrical tab decide the connector lines.
| Harness | String fuses | Connector lines |
|---|---|---|
| One string per input | Inline, or inline and inside the device | DC connector, male and female, plus DC connector set with inline fuse |
| One string per input | Inside the device, or none | DC connector, male and female |
| Y | Inline, or inline and inside the device | Y connector set with fused arms, one per pair |
| Y | Inside the device, or none | Y connector set, one per pair |
Under a Y, a string with a cable of its own keeps its own connectors. The DC solar cable splits: each string's own cable before the Y is at String cable size, and the shared cable after it at Y pair cable size.
Cable laying
The laying choices on the Cables card reach the BOM at the next Generate.
| Laying | Lines it brings |
|---|---|
| DC string cable in conduit, buried or above ground | HDPE DWC conduit · for DC cables, along the route, and five manual conduit fittings |
| DC string cable, AC cable or DC trunk above ground | Concrete block for above-ground laying, the route divided by Concrete block spacing, rounded up |
| DC string cable above ground | UPVC clamp · above-ground laying, one per block |
| AC cable above ground | UPVC clamp · above-ground laying of LV AC cable, each cable divided by the spacing, rounded up |
| MV cable on tray | Ladder cable tray · for MV cable, along the MV route |
Cable tie · DC cable along the tables and trackers is counted with or without cables, from Cable tie spacing.
Communication and weather stations
| Choice | Lines |
|---|---|
| Power-line, over the AC cable | SACU and PLC box, one per ICR |
| RS485, daisy-chained | RS485 cable, and Communication cable termination · RS485, eight per cable end |
| A weather station | The station, 50 m of RS485 cable, 50 m of conduit and 16 terminations |
| Module sensors at every ICR | Weather monitoring station · module temperature only, one per ICR |
Each ICR with an MV run has Optical fibre cable as long as that run, so there is no fibre without an MCR, USS or handover point. A chain longer than the limit in Advanced settings puts a remark on the RS485 line.
MV network
The network is radial.
- MV breaker panel (ICOG): one per ICR, with an incomer per IDT.
- HT panel · at the MCR: its incomers are the feeders and the USS links. HT panel · at a USS follows the same idea. A handover point has no panel.
- MV cable: one row per cable schedule row, length × runs.
- MV straight-through joint kit: runs × one fewer than the number of drums a run takes, from MV cable drum length.
- Inverter duty transformer: split per rating and winding count, such as "16,000 kVA, 33 kV / 800 V, 5-winding, ONAN, Aluminium windings". See ACCB and transformers.
When a solar park provides the main control room, several of these go. See Grid connection by others.
Earthing
Earthing is measured from the project's earthing design, without opening its window: pits by duty, strips by class, and two bolt sets per jumper or bridge. See Earthing design.
Cleaning fleet and arresters
Cleaning robot and Cleaning robot bridge appear once a fleet is sized in Robotic module cleaning, with one bridge line per kind, standard or supported. Lightning arrester, ESE prints the protection level and mast height in its specification, such as "Level IV, 9 m mast". See Lightning arresters.
Where to go next
BOM profiles
A profile holds the items, specifications, makes and allowances a BOM starts from. How to create, import, share and choose one, and save edits into it.
Exports overview